Infrastructure of MPIZ

  22/04/2016

Internal roads::

The system of internal roads with an area of 26 hectares, accounting for 11.27% of the total land area built a complete and synchronized within the industrial zone, including the main road is 2 way, 4 lanes with 68m, 34m and 31m wide.

Along the road is 8m wide sidewalks are layout of underground technical hallways such as electricity, water supply, communications. All the internal roads are arranged lighting system.

Power supply systems:

MP Dinh Vu Industrial Zone is powered from the national grid through power stations maximum capacity 45MW. Electrical connection points are available at the specified location with 22KV voltage.

HTKT

Image: Dinh Vu power station

Water supply system:

Water for MP Dinh Vu industrial zone is supplying with a maximum capacity of 5000m3 / day. Besides industrial zone also arranged a reserve water tank in case of emergency.

Drainage and sewage system:

The system of drainage and sewage are built separately. Rainwater is collected through drains and drainage system in the area of the river. Diameter of the drainage sewers D800mm -D1000mm the principles of free flowing.

Industrial waste water is collected in underground sewer system and via intermediate pump stations and are processed at waste water treatment plants before discharge into the environment.

Fire protection systems:

Modern fire protection system advanced, synchronized with the base infrastructure to meet the requirements of fire prevention, fire fighting. Water supply piping system and fire fighting water cylinder is arranged on the entire internal routes.